Tentative Master Schedule Generation - Batch - Reports

MS170E

Number

Description

Purpose

MS170A

Tentative Master Schedule Generation Request

Tentative Master Schedule Generation Request lists the parameters of every Tentative Master Schedule Generation request entered.  Any error or warning messages are also printed after the corresponding request.

MS170B

Tentative Master Schedule

Tentative Master Schedule is printed by the Tentative Master Schedule Generation program (MS170E), but only if the user specifically requests it.  The report shows the quantities that should be produced weekly to meet projected demand and target inventory levels.  The projected inventory level and other key quantities are printed for comparison purposes.  Time fences and any other warning messages are also printed.
Other relevant quantities are shown for comparison against the newly calculated tentative master schedule.  The report is organized to reflect the planning period option the user selected.
The report also prints the consumption code.  This code will cause the MS and RP planning programs to "net" or "consume" against the forecast either only certain types of demand or all types of demand for the part.

MS170C

Tentative Master Schedule Generation Error

Tentative Master Schedule Generation Error lists all tentative master schedule generation requests for which an exception or error condition occurred during processing.  If all requests are successfully processed, this report is not printed.