RP Selective Request Maintenance - Purpose
RP120E
The RP Selective Request Maintenance program (RP120E) is called directly from the Requirements Planning Generation Request program (RP110E) when the user chooses a selective requirements planning generation. All requests for the particular plant specified in RP110E are displayed and the user has the option of adding new requests or deleting existing ones. RP110E will inform RP120 of when the programs are running in actual or simulation request mode.
When the program is called, a window is displayed over the bottom half of the RP110E screen containing all of the requests for the plant.