The Cumulative Leadtime Generation Request program (DE350E) allows the user to request that cumulative leadtimes be recalculated and updated for all parts within a plant. The request is placed on Reference File category K11. Only one request is allowed per plant. If a request has already been entered, this program retrieves the request from K11 and allows the user to update it. Note that category K11 cannot be maintained directly, it must be updated through this program.
The request is processed by the Cumulative Leadtime Generation program (DE580E), which recalculates cumulative lead time, updates the Part Master program if the new lead time is different than the old, and prints the Cumulative Leadtime Generation report (DE580) to record any changes.