IA670A
|
Burden Efficiency Detail Report
|
This report lists the actual, standard, and variance overhead costs for each manufacturing order. In all cases, the cost equals the corresponding hours times the overhead (or burden) rate.
Both open and closed orders are included in the report. In addition, the hours used to calculate the costs and the efficiency rate are provided for each manufacturing order. Hour subtotals, cost subtotals, and efficiency rate are also given for each operation, part, workcenter, department, plant, and company.
|
IA670B
|
Burden Efficiency Summary Report
|
This report lists the actual, standard, and variance overhead costs for each workcenter. In all cases, the cost equals the corresponding hours times the overhead (or burden) rate.
Both open and closed orders are included in the report. In addition, the hours used to calculate the costs and the efficiency rate are provided for each workcenter. Hour subtotals, cost subtotals, and efficiency rate are also given for each department, plant, and company.
|