WILLIAMS PLT BEL MASTER SCHEDULING 2/02/93
DSP01 ROLLOVER REQUEST REVIEW
Full or Selective Rollover (F/S) S
Planner Code P
Part Number
Starting Date 020293
Horizon Date 010594
Change Quantity Filter 00
Print MS Action Report (Y/N) Y
F3=Exit F5=Previous F6=Next F9=Enter Mode
F14=Delete F21=New Ref ID
This screen is used to review the Master Schedule Rollover Report request screen.
PLANT
Display only. Used to identify the plant for which the M/S rollover will be done.
FULL OR SELECTIVE ROLLOVER
Display only. Valid values are:
F - Full. All master scheduled parts will be processed.
S - Selective. Selected parts will be processed, based on the Planner Code or Part Number specified.
PLANNER CODE
Display only. A Selective Rollover will process all parts for the particular planner displayed.
PART NUMBER
Display only. If you wish to process a single part only, request a Selective Rollover and enter the Part Number.
STARTING DATE
Display only. The starting date for which the tentative schedule will be implemented. Greater than or equal to the current week start date.
HORIZON DATE
Display only. The ending date for the rollover process.
CHANGE QUANTITY FILTER
Display only. The Quantity Filter allows you to suppress action messages for minor scheduling changes. The filter represents the difference between current orders and the tentative master schedule, expressed as a percentage of the tentative master schedule, that will be ignored during the rollover process.
PRINT ACTION REPORT OPTION
Display only. Valid values are:
Y - Print the Planning Action Report
N - Do not print the Action Report If 'Y' is selected, you may select reporting options on a subsequent screen.
COMMAND KEYS
F3 - Exit to menu.
F5 - Display previous transaction.
F6 - Display next transaction.
F9 - Return to the screen from which you requested the transaction review.
F14 - Delete this transaction.
F21 - New Reference ID.
|