WILLIAMS   PLT BEL            MASTER SCHEDULING                        5/31/94

 DSP01                AVAILABLE TO PROMISE REPORT REQUEST                DETAIL

                                                                                

                      Full Report or By Planner (F/P)  F                       

                                                                               

                      Planner Code                                             

                                                                               

                      Horizon Date                     062894                  

                                                                               

                      Planning Period Option           1                       

                                                                               

                      Planning Method                  M                       

                                                                               

                      Exception Only                   N                       

                                                                               

                   Planning Period Options:       Planning Method:             

                    1. Calendar Weeks              D - Daily                   

                    2. Calendar Months             M - Master Scheduled        

                    3. Calendar Periods                                        

                    4. Daily Intervals                                         

                                                                               

 F2=Command          F3=Exit             F4=Prompt           F9=Review         

 F16=Change Printer  F17=New Plant                                             

                                                                               

 

 

This screen is used to request the Available to Promise Report, which compares scheduled production, projected demand, and firm demand.  The report assists the planner in determining the quantity available to be promised, and in identifying the next future period in which inventory will be available.

PLANT

Required.  Used to identify the plant for which the Available to Promise Report should be shown.  Plant must be valid (not blanks or nines) and the user must be authorized to the manufacturing company/warehouse associated with the plant (Reference File category 409).  Defaults to the plant assigned to the user ID, but may be changed by pressing F17.

FULL REPORT OR BY PLANNER (F/P)

Required.  Valid Values are:

F - Full Report.  All master scheduled parts will be printed on the Available to Promise Report.

P - Selected Report by Planner.  Only those master scheduled parts planned by the requested planner will be printed on the Available to Promise Report.

PLANNER CODE

Required if Report by Planner is selected.  Specifies the planner that will be used to select parts to print on the Available to Promise Report.

HORIZON DATE

Required.  The ending date for which information will be printed on the Available to Promise Report.

PLANNING PERIOD OPTION

Required.  Specifies the periods for which availability information will be summarized and reported.

1 - Calendar Weeks

2 - Calendar Months

3 - Calendar Periods

4 - Daily Intervals

PLANNING METHOD

Required.  If you request the daily planning method (option D), daily master scheduled parts will be selected.  If you request the master scheduled planning method (option M), standard master scheduled parts will be selected.  The value will default from Reference File category 464.

EXCEPTION ONLY

Optional.  If this flag is set to Y (yes), only parts having a negative cumulative available to promise within the horizon will be printed.  If this flag is set to N (no), all parts matching the selection criteria will be printed.  This field will default to N.

COMMAND KEYS

Enter - Request the report.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit without update.

F4    - Display a list of values for the field where the cursor is positioned.  If you select one of the items from the list, it will be returned to the application screen.

F9    - Enter the Transaction Review program to review and delete report request.

F16   - Allows the user to change the output location.

F17   - Used to change the plant in which the user is currently working.