MS310S01 - Planned Routing Generation Request

 

 

WILLIAMS                      MASTER SCHEDULING                        2/10/92

 DSP01                 PLANNED ROUTING GENERATION REQUEST                DETAIL

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

                                                                               

                                                                               

                                                                               

                                                                                

                             Submit Request        X                           

                                                                               

                                                                               

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

                                                                               

                                                                               

 F2=Command          F3=Exit                                                   

                                                                               

                                                                                

 

 

This screen is used to submit a request for planned routing generation.  A Planned Routing is generated for each master scheduled or service part.  The Planned Routing is a load profile which reflects the relationship between a part and the key facilities it requires, considering all levels of the bill of material.  The Planned Routing is used in Key Facility Load Reporting.  The routing need not be regenerated for key facility load reporting unless the bill of material, routing, average order quantity, master scheduling order quantity, or key facility definition changes.

SUBMIT REQUEST

Optional.  Enter an 'X' to request the Planned Routing Generation.

COMMAND KEYS

Enter - Request Planned Routing Generation.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.