MS330S01 - Rollover Request Select

 

 

WILLIAMS   PLT BEL            MASTER SCHEDULING                        2/10/92

 DSP01                          ROLLOVER REQUEST                         SELECT

                                                                               

                                                                               

                                                                               

                Full or Selective Rollover (F/S) F                             

                                                                               

                Planner Code                                                   

                                                                                

                Part Number                                                    

                                                                               

                Starting Date                    021092                        

                                                                               

                Horizon Date                     061592                        

                                                                                

                Change Quantity Filter                                         

                                                                               

                Print MS Action Report (Y/N)     Y                             

                                                                               

                                                                               

                                                                                

 F2=Command          F3=Exit             F4=Prompt           F9=Review         

 F15=Rekey Data      F17=New Plant                                             

                                                                               

 

 

This screen is used to request a Master Schedule Rollover.  The Rollover process implements the tentative master schedule as planned manufacturing orders, planned transfer and purchase requisitions, and flow schedules.  In this process, the tentative master schedule is compared to actual manufacturing orders, transfer and purchase requisitions, and JIT flow schedules, and where they do not correspond to current netted demand, they are modified or created, or action messages for firm and open orders, requisitions, and flows are printed.  The Rollover may be requested for all standard master scheduled parts, one particular part, or all parts planned by a specified planner.

PLANT

Required.  Used to identify the plant for which the Master Schedule Rollover will be done.  The plant must be valid (not blanks or nines) and the user must be authorized to the manufacturing company/warehouse associated with the plant (Reference File category 409).  Defaults to the plant assigned to the user ID, but may be changed by pressing F17.

FULL OR SELECTIVE ROLLOVER

Required.  Valid values are:

F - Full.  All standard master scheduled parts will be processed.

S - Selective.  Selected parts will be processed, based on the Planner Code or Part Number specified.

PLANNER CODE

Optional.  If you wish to process all parts for a particular planner, request a Selective Rollover and enter the planner code.

PART NUMBER

Optional.  If you wish to process a single part only, request a Selective Rollover and enter the part number.  It must be a standard master scheduled part, not a daily master scheduled, requirements planning, or service part.

STARTING DATE

Required.  The starting date for which the tentative schedule will be implemented.  Must be greater than or equal to the current week start date.  Note:  If the net change flag of the part being processed is equal to replan (2), all planned orders for the part must be regenerated and as a result, the current week start date will override the date entered here. 

HORIZON DATE

Optional.  The ending date for the rollover process.  Note:  If the net change flag of the part being processed is equal to replan (2), all planned orders for the part must be regenerated and as a result, the horizon date will equal the greater of the dates entered here and the due date of the last planned order for the part.

CHANGE QUANTITY FILTER

Optional.  The Quantity Filter allows you to suppress action messages for minor scheduling changes.  The filter represents the difference between current orders and the tentative master schedule, expressed as a percentage of the tentative master schedule, that will be ignored during the rollover process.

PRINT ACTION REPORT OPTION

Required.  Valid Values are:

Y - Print the Planning Action Report

N - Do not print the Action Report If 'Y' is selected, you may select reporting options on a subsequent screen.

COMMAND KEYS

Enter - Request the Master Schedule Rollover.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit with update.

F4    - Display a list of values for the field where the cursor is positioned.  If you select one of the items from the list, it will be returned to the application screen.

F9    - Enter the Transaction Review program to review and delete report requests.

F15   - Rekey the entered data.

F17   - Used to change the plant in which the user is currently working.