WILLIAMS KEY FACILITY LOAD 7/28/94
DSP01 Planned Routing Date : 3/28/94 SUMMARY
Key Facility KF1 Period : 1/10/94 - 12/31/94 CALENDAR WEEKS
.............................................................. TATIVE SCHEDULE
: Key Facility KF1 KEY FACILITY 1 :
: Effective Capacity Hrs-1 100 Ending Date 0/00/00 : ---------------
: Effective Capacity Hrs-2 Ending Date 0/00/00 : 01/17/94
: Effective Capacity Hrs-3 : .000
: Efficiency Percent 100 : .000
: Utilization Percent 100 :
: Load Units HOURS Hours Per Day 10 :
: :
:............................................................:
Total .000 .000 5000.000 116050.000
Capacity 40.000 40.000 40.000 40.000
Percentage Load .00 .00 999.00 999.99
F6=Next Screen F7=Plan Act Review F9=Maintenance
F11=Order Detail F12=Fold/Truncate F13=Simul Maint F24=More Keys
The Key Facility Window provides information about the key facility that was entered on the Function Select screen. This window is accessed by pressing F16 from the Summary screen (MS800S02) in Key Facility Inquiry. To exit from this screen press Enter.
KEY FACILITY
Display only. This is the key facility for which information is being displayed. It was entered on the Function Select screen.
KEY FACILITY DESCRIPTION
Display only. The key facility description appears on various reports and inquiries. It describes the key facility.
EFFECTIVE CAPACITY HOURS -1
Display only. This field specifies the optimal capacity for the key facility in hours per working week. The Effective Capacity Hours are compared with the calculated load (Total Run Hours) for the key facility for the week to determine whether or not the key facility is overloaded.
ENDING DATE - 1
Display only. This specifies the ending date for the corresponding effective capacity hours. Three capacity periods may be defined to reflect declining efficiency of machines, planned acquisitions of machines, additional shifts, larger work crews, etc.
EFFECTIVE CAPACITY HOURS -2
Display only. This field specifies the optimal capacity for the key facility in hours per working week.
ENDING DATE - 2
Display only. This field specifies the ending date for the corresponding effective capacity hours.
EFFECTIVE CAPACITY HOURS - 3
Display only. This field specifies the optimal capacity for the key facility in hours per working week.
EFFICIENCY PERCENT
Display only. This field defines the standard efficiency of the key facility.
UTILIZATION PERCENT
Display only. This defines the standard utilization of the key facility.
LOAD UNITS
Display only. The load units is a descriptive measure of the type of load to be calculated for this key facility. If the load for this key facility is to be determined using information created from the routing file (Using Planned Routing Generation), the load units should be expressed in hours. If the load for this key facility is to be determined using a resource profile, the load units should correspond to the load being measured in the resource profile.
HOURS PER DAY
Display only. This field is displayed on the key facility load report and inquiry. There is no calculation associated with this field.
|