MAC-PAC Homecontact ussupport login 
Documentation > MAC-PAC Reference Library > Manufacturing > Master Scheduling > Screens > Key Facility Load > KFS01 - Key Facility Window

KFS01 - Key Facility Window

 

 

WILLIAMS                      KEY FACILITY LOAD                        7/28/94

 DSP01                   Planned Routing Date :  3/28/94                SUMMARY

 Key Facility       KF1   Period :   1/10/94 - 12/31/94          CALENDAR WEEKS

 .............................................................. TATIVE SCHEDULE

 : Key Facility       KF1  KEY FACILITY 1                     :                

 : Effective Capacity Hrs-1     100  Ending Date      0/00/00 : ---------------

 : Effective Capacity Hrs-2          Ending Date      0/00/00 :     01/17/94   

 : Effective Capacity Hrs-3                                   :            .000

 : Efficiency Percent       100                               :            .000

 : Utilization Percent      100                               :                

 : Load Units       HOURS            Hours Per Day   10       :                

 :                                                            :                

 :............................................................:                

                                                                               

                                                                               

                                                                                

                                                                               

 Total                     .000            .000        5000.000      116050.000

 Capacity                40.000          40.000          40.000          40.000

 Percentage Load           .00             .00          999.00          999.99 

                                                                               

                     F6=Next Screen      F7=Plan Act Review  F9=Maintenance    

 F11=Order Detail    F12=Fold/Truncate   F13=Simul Maint     F24=More Keys     

                                                                               

 

The Key Facility Window provides information about the key facility that was entered on the Function Select screen.  This window is accessed by pressing F16 from the Summary screen (MS800S02) in Key Facility Inquiry.  To exit from this screen press Enter.

KEY FACILITY

Display only.  This is the key facility for which information is being displayed.  It was entered on the Function Select screen.

KEY FACILITY DESCRIPTION

Display only.  The key facility description appears on various reports and inquiries.  It describes the key facility.

EFFECTIVE CAPACITY HOURS -1

Display only.  This field specifies the optimal capacity for the key facility in hours per working week.  The Effective Capacity Hours are compared with the calculated load (Total Run Hours) for the key facility for the week to determine whether or not the key facility is overloaded.

ENDING DATE - 1

Display only.  This specifies the ending date for the corresponding effective capacity hours.  Three capacity periods may be defined to reflect declining efficiency of machines, planned acquisitions of machines, additional shifts, larger work crews, etc.

EFFECTIVE CAPACITY HOURS -2

Display only.  This field specifies the optimal capacity for the key facility in hours per working week.

ENDING DATE - 2

Display only.  This field specifies the ending date for the corresponding effective capacity hours.

EFFECTIVE CAPACITY HOURS - 3

Display only. This field specifies the optimal capacity for the key facility in hours per working week.

EFFICIENCY PERCENT

Display only.  This field defines the standard efficiency of the key facility.

UTILIZATION PERCENT

Display only.  This defines the standard utilization of the key facility.

LOAD UNITS

Display only.  The load units is a descriptive measure of the type of load to be calculated for this key facility.  If the load for this key facility is to be determined using information created from the routing file (Using Planned Routing Generation), the load units should be expressed in hours.  If the load for this key facility is to be determined using a resource profile, the load units should correspond to the load being measured in the resource profile.

HOURS PER DAY

Display only.  This field is displayed on the key facility load report and inquiry.  There is no calculation associated with this field.