Tentative Master Schedule Generation Request
MS170A
DATE 6/17/94 PAGE 1
TIME 12:24:42 PLANT BEL
REPORT MS-170A TENTATIVE MASTER SCHEDULE GENERATION REQUEST
SEQ FL/ PLN START HORIZON PLN ---------------------------- ERROR -----------------------------
NO REF ID SEL CDE PART NUMBER DATE DTE PER PRT CODE MESSAGE
---- ---------- - - --------------- -------- -------- - - ------- -------------------------------------------------------
0001 WILLIAMS S EMB BOLT-100 4/28/94 5/19/94 1 Y
MPW0324 Requested date before current week - Current week used
MPC1440 Horizon date must be greater than start date
0002 WILLIAMS S ADM BOLT-200 6/20/94 7/06/94 1 Y
END OF REPORT
|