Master Scheduling Rollover Requests
MS180
DATE 2/11/92 ANDERSEN SOFTWARE PAGE 1
TIME 10:42:55 RUE DE GRAND CHIEN 1
REPORT MS-180
MASTER SCHEDULING ROLLOVER REQUESTS
SEQ FL/ PLN START HORIZON ---- P R I N T O P T I O N S ----
NO REFERENCE SEL CDE PLT PART NUMBER DATE DTE PRNT PART DTE STRT DTE HRZN DTE
---- ---------- --- --- --- --------------- -------- -------- ---- ---- ---- -------- --------
0001 USERA F BEL 2/11/92 6/16/92 Y 1 1 0/00/00 0/00/00
MRP-MASTER-PAR MPW0307 No schedule exists for part within horizon
** END OF REPORT **
|
Purpose
The Master Scheduling Rollover Requests Report prints out the parameters that were used to control the Master Scheduling Rollover Program (MS180E) and messages for any errors that occurred during processing.
Report Sequence
None.