Processing
The Master Schedule Rollover implements the tentative Master Schedule by performing a week-by-week comparison of the tentative schedule quantity to the actual schedule quantity. Where differences are found, the system either implements schedule changes (by adding, deleting, or changing planned orders) or suggests changes to existing firm or open orders. The resulting schedule and any suggested schedule changes are printed on the Action Report.