DSP01 REFERENCE FILE CATEGORY D03 FUNCTION SELECT
Category Name COMMODITY CD PRINT PARM
COMM CODE(3) PLANT(3)
Category Key METBEL
XXXXXX
Request Code 4
1 - Add
2 - Change
3 - Delete
4 - Inquire
F2=Command F3=Exit F7=End Category F8=Display List
F9=Inquiry
The Commodity Code Print Parameters Category defines what information will appear on the Planning Action Report (RP520B) for a particular commodity code.
COMMODITY CODE
Required. Enter a valid commodity code from Reference File category 434.
PLANT
Required. Enter the plant with which the Commodity Code Print Options should be associated for the given commodity code.
Detail
RFD03S02 - Detail
WILLIAMS COMMON FEATURES 2/12/92
DSP01 REFERENCE FILE CATEGORY D03 INQUIRE
Category Name COMMODITY CD PRINT PARM
COMM CODE(3) PLANT(3)
Category Key METBEL
PLANNING FACTOR JIT PLAN DAYS PRINT EXCEPTION ONLY
Data 040 030 N
NND NNN Y
PRINT BEYOND HORIZON PLANNED ORDER EXCEPTION
Data Y N
Y Y
RE-SCHEDULE EARLY RE-SCHEDULE LATE
Data 00 00
NN NN
F2=Command F3=Exit F9=Inquiry F10=Function Select
PLANNING FACTOR
Required. Used to determine a planning horizon for a commodity code. The value entered is multiplied by the cumulative lead time for each part processed, resulting in the number of days across which requirements will be analyzed.
JIT PLANNING DAYS
Required. The days defining the planning horizon for JIT parts with this commodity code.
PRINT EXCEPTIONS ONLY FILTER
Required. Valid values are:
Y- Print only those items with this commodity code that have order action messages.
N- Print all items processed that have this commodity code.
PRINT BEYOND HORIZON FILTER
Required. Valid values are:
Y- Allow exceptions beyond the planning horizon to force printing of the planning action report. Exceptions are displayed.
N- Ignore exceptions beyond the planning horizon.
PLANNED ORDER EXCEPTION FILTER
Required. Valid values are:
Y- Treat planned orders as exceptions.
N- Ignore planned orders.
RE-SCHEDULE EARLY FILTER
Required. Used to suppress action messages for minor changes in schedule. Expedite messages will be printed only if the order should be brought forward by a number of days that is greater than the filter.
RE-SCHEDULE LATE FILTER
Required. Used to suppress action messages for minor changes in schedule. Defer messages will be printed only if the order should be delayed by a number of days that is greater than the filter.