Master Schedule Load Quantity
This field represents an average production quantity for Master Scheduled parts. Master Scheduling uses this quantity in Rough Cut Capacity Planning to calculate the load at each key facility against the tentative or final master schedule. The Master Schedule Load Quantity is not used for costing purposes.