DATE     3/18/92                                 ANDERSEN SOFTWARE                                                         PAGE    1

TIME    11:47:24                                                                                                             CO  001

REPORT  SF535B                                             SCRAP EXPENSE SUMMARY                                            LOC  BER

                                                     FROM  10/01/91  TO   3/18/92      REQUESTOR:                         PLANT  GER

DEPARTMENT                           SCRAP

  NUMBER                            QUANTITY      MATERIAL EXPENSE      LABOR EXPENSE        BURDEN EXPENSE      TOTAL SCRAP EXPENSE

----------                        ------------   ------------------   ------------------   ------------------    -------------------

   P01                                  38.000              821.00               279.90                74.96               1,175.86

                                  ------------   ------------------   ------------------   ------------------    -------------------

      PLANT TOTALS   :  GER             38.000              821.00               279.90                74.96               1,175.86

                                  ------------   ------------------   ------------------   ------------------    -------------------

      CO/LOC TOTALS: 001 BER            38.000              821.00               279.90                74.96               1,175.86

                                  ============   ==================   ==================   ==================    ===================

Purpose

The Scrap Expense Summary Report includes information about all scrap transactions reported between two dates.  The report can be requested for a specific department within a plant, for all departments within a plant, or for all plants.  Totals are accumulated by department, plant, and company/location for quantity scrapped, material cost due to scrap, labor cost due to scrap, overhead cost due to scrap, and total cost due to scrap.

Report Sequence

Department number, plant, company/location