Scrap Expense Detail Report
SF535A
DATE 3/18/92 ANDERSEN SOFTWARE PAGE 3
TIME 11:47:23 CO 001
REPORT SF535A SCRAP EXPENSE DETAIL LOC BER
FROM 10/01/91 TO 3/18/92 REQUESTOR: PLANT GER
DEPARTMENT NUMBER: P01 PAINT DEPARTMENT
WORKCENTER : WC3 WORKCENTER THREE
SCRAP SCRAP
PART NUMBER PART DESC CODE QUANTITY MATERIAL EXPENSE LABOR EXPENSE BURDEN EXPENSE TOTAL SCRAP EXPENSE
--------------- -------------------- ----- ------------ ------------------ ------------------ ------------------ -------------------
SIDE-OO1 SIDE PANEL HA 6.000 186.00 17.40 10.92 214.32
------------ ------------------ ------------------ ------------------ -------------------
PART TOTALS : SIDE-001 6.000 186.00 17.40 10.92 214.32
AXLE-2000 AXLE/20"" DM 2.000 20.00 .00 .00 20.00
------------ ------------------ ------------------ ------------------ -------------------
PART TOTALS : AXLE-2000 2.000 20.00 .00 .00 20.00
BLA-2000 BLADE/20"" DM 3.000 15.00 .00 .00 15.00
------------ ------------------ ------------------ ------------------ -------------------
PART TOTALS : BLA-2000 3.000 15.00 .00 .00 15.00
------------ ------------------ ------------------ ------------------ -------------------
WORKCENTER TOTALS : WC3 11.000 221.00 17.40 10.92 249.32
------------ ------------------ ------------------ ------------------ -------------------
DEPARTMENT TOTALS : P01 38.000 821.00 279.90 74.96 1,175.86
------------ ------------------ ------------------ ------------------ -------------------
PLANT TOTALS : GER 38.000 821.00 279.90 74.96 1,175.86
------------ ------------------ ------------------ ------------------ -------------------
CO/LOC TOTALS: 001 BER 38.000 821.00 279.90 74.96 1,175.86
============= ================== ================== ================== ===================
|
Purpose
The Scrap Expense Detail Report lists all scrap transactions reported between two dates. The report can be requested for a specific department within a plant, for all departments within a plant, or for all plants. Totals are accumulated by scrap code, part, workcenter, department, plant, and company/location for quantity scrapped, material cost due to scrap, labor cost due to scrap, overhead cost due to scrap, and total cost due to scrap.
Report Sequence
Transaction date, scrap code, part number, workcenter number, department number, plant, company/location