Planning Action for JIT Parts
RP520C
DATE 2/11/93 ANDERSEN SOFTWARE EUROPE PAGE 1
TIME 12:40:55 MANUFACTURING WAREHOUSE PLANT FCW
REPORT RP-520C PLANNER AAA
VENDOR PLANNING ACTION REPORT FAMILY ID
PART NUMBER/ PART PRD PLN PLAN POL COM YIELD QUEUE PROD FIRM NET PLANNING NON-PLANNING
DESCRIPTION UM TYPE TYP POL QTY / INCR CDE FACTR DAYS CENTER HORIZON INV BALANCE BALANCE
---------------------- -- ---- --- --- ---------- --- ----- ---- ------- -------- - ------------ ------------
POTJITA EA MFG JIT PTL .000 .00 .0 JTPC01 N 370.000 .000
JIT POTENCY CNTLD PART
----- R E Q U I R E M E N T S ------- --------- S U P P L Y ---------- -------- A C T I O N --------
PARENT PART NO/ ORD NO/ PROJECTED ORD NO/ ORD O RESULTING
DATE CUSTOMER NUMBER PRD CTR QUANTITY INVENTORY YIELD PRD CTR TYP S REQ NO MSG QUANTITY INVENTORY
-------- --------------- -------- ------------ ------------ ---------- ------- --- - ------- ----- ---------- ------------
1/26/93 CUS-APG-GERMANY JIT00100 44.000 326.000
1/26/93 326.000
2/11/93 370.000 44.000 JTPC01 FLW P
2/11/93 370.000
2/11/93 ---------------------------------------------------------------------------------------------------------------------------
ACTIVITY NOT SHOWN BEYOND HORIZON .000 .000
MPW1657 Beginning balance(s) calculated in potent units
MPW1658 Part's standard potency in this plant is 100.00
END OF PLANNING DETAIL FOR PART
|
Purpose
The Planning Action Report lists either the simulated or actual results of the Requirements Planning Generation for JIT Parts Program (RP105E). This report provides the following information for each part:
· Descriptive part information
· Time-phased detail of all requirements and supply
· A projected inventory level adjusted by existing requirements and supply
· Order action messages to suggest a response to maintained production if a surplus or shortage will occur
· A resulting inventory level if the suggested order action is initiated
Each requirement is pegged to its origin.
Report Sequence:
Planner, Part Number, Required Date (Requirements) or Supply Date (suggested production schedule).