Planning Action Overview

RP540B

 


 

DATE        7/15/94                              ANDERSEN CONSULTING APPLICATIONS, INC                                     PAGE   1

TIME       16:20:46                              PICKING & SHIPPING INC

REPORT     RP540B

REQUESTOR  WILLIAMS                                  PLANNING ACTION OVERVIEW REPORT                  LAST R/P RUN DATE      7/15/94

                                                       SELECTED OPTIONS:

                                                       REPORT SEQUENCE:   3

                                                           1 - VENDOR NUMBER

                                                           2 - PLANNER

                                                           3 - PART

                                                           4 - BUYER

                                                       PERIOD OPTION:      WEEKLY

                                                       SELECTION:

                                                           PLANT          BEL

                                                           VENDOR

                                                           PLANNER

                                                           FAMILY ID

                                                           PART NUMBER    ACCAR

                                                           PART TYPE

                                                           ABC CLASS

                                                           PLAN POLICY

                                                           RP RUN MODE    A

                                                           BUYER

                                                           DAILY MS PARTS Y

                                                           RP PARTS       Y

                                                           SERVICE PARTS  Y


 

DATE        7/15/94                              ANDERSEN CONSULTING APPLICATIONS, INC                                     PAGE   2

TIME       16:20:46                              PICKING & SHIPPING INC

REPORT     RP540B

REQUESTOR                                         PLANNING ACTION OVERVIEW REPORT

                                                  PLANNING ACTION OVERVIEW REPORT                     LAST R/P RUN DATE      7/15/94

Part Number        UM   Before     7/15/94    7/18/94    7/25/94    8/01/94    8/08/94    8/15/94    8/22/94    8/29/94    After

--------------     -- ---------- ---------- ---------- ---------- ---------- ---------- ---------- ---------- ---------- ----------

BICYCLE            EA 10-SPEED BICYCLE           Planning Balance:           .000

        Demand           353.000    180.000    420.000    440.000    580.000    420.000    440.000    580.000    420.000    520.000

        Proj Inv         547.000    367.000     67.000    133.000-   533.000-   720.000-   840.000-  1080.000-  1260.000-  1500.000-

        Coverage           1.54       2.03        .15        .30-       .91-      1.71-      1.90-      1.86-      3.00-      2.88-

        Transfers Out       .000       .000       .000       .000       .000       .000       .000       .000       .000       .000

                                                      **  END OF PART  **

                                                            **  END OF REPORT  **

Purpose

The Planning Action Overview Report summarizes either the actual or simulated results of the Requirements Planning Generation programs (RP100E for MRP parts and RP105E for JIT parts).  The overview report shows the total demand, projected inventory (based on the current schedule), and coverage (projected inventory divided by demand) for each period.

For more information about what specific changes are recommended, the user should request the Planning Action Detail Report (RP530A and RP530B).

This report is requested through the Planning Action Summary Report option on the Requirements Planning Application Menu. 

Report Sequence:

One of the following sequences, as specified on the report request screen:

·     Vendor Number, Part Number, Plant, Buyer

·     Planner, Part Number, Plant

·     Part Number, Plant