MAC-PAC Homecontact ussupport login 
Documentation > MAC-PAC Reference Library > Manufacturing > Requirements Planning > Reports > Planning Action Detail for JIT Parts

Planning Action Detail for JIT Parts

RP530B

 


 

DATE     2/11/93                              STEVENS SUPPLY                                                         PAGE          1

TIME    14:20:41                                                                                                     PLANT       FCW

REPORT  RP-530B                                        PLANNING ACTION REPORT                                        PLANNER     AAA

VENDOR                                                                               REQUESTOR WILLIAMS              FAMILY ID

PART NUMBER/                        PART PRD PLN  PLAN POL  COM YIELD QUEUE  PROD     FIRM   NET    PLANNING    NON-PLANNING

DESCRIPTION                      UM TYPE TYP POL QTY / INCR CDE FACTR DAYS  CENTER   HORIZON INV    BALANCE       BALANCE

----------------------           -- ---- --- --- ---------- --- ----- ----  ------- --------  -   ------------  ------------

JIT PART                         EA MFG  JIT PTL       .000       .00   .0  JTPC01            N        370.000          .000

JIT POTENCY CNTLD PART

         ----- R E Q U I R E M E N T S -------              --------- S U P P L Y ----------  -------- A C T I O N --------

         PARENT PART NO/ ORD NO/                PROJECTED              ORD NO/ ORD O                            RESULTING

  DATE   CUSTOMER NUMBER PRD CTR   QUANTITY     INVENTORY     YIELD    PRD CTR TYP S REQ NO    MSG   QUANTITY   INVENTORY

-------- --------------- -------- ------------ ------------ ---------- ------- --- - -------  ----- ---------- ------------

 1/26/93 CUS-APG-GERMANY JIT00100       44.000      326.000

 1/26/93                                                                                                            326.000

 2/11/93                                            370.000     44.000 JTPC01  FLW P

 2/11/93                                                                                                            370.000

 2/11/93 ---------------------------------------------------------------------------------------------------------------------------

ACTIVITY NOT SHOWN BEYOND HORIZON         .000                    .000

                                                                         MPW1657 Beginning balance(s) calculated in potent units

                                                                         MPW1658 Part's standard potency in this plant is 100.00

                                                                         END OF PLANNING DETAIL FOR PART

                                                                             **  END OF REPORT  **

Purpose

The Planning Action Detail Report lists the calculated results of the Requirements Planning Generation for JIT Parts Program (RP105E).  This report provides the following information for each part:

·     Descriptive part information

·     Time-phased detail of all requirements and supply

·     A projected inventory level adjusted by existing requirements and supply

·     Order action messages to suggest a response to maintained production if a surplus or shortage will occur

·     A resulting inventory level if the suggested order action is initiated

Each requirement is pegged to its origin.

Report Sequence:

Planner, Part Number, Required Date (Requirements) or Supply Date (suggested production schedule).