MAC-PAC Homecontact ussupport login 
Documentation > MAC-PAC Reference Library > Manufacturing > Product Costing > Screens > Product Cost Analysis > PC810S07 - Labor

PC810S07 - Labor

 

 

 

 

WILLIAMS                   PRODUCT COST ANALYSIS           BEF         3/05/93

 DSP01                       LABOR - CURRENT COST                              

   EFFECTIVITY DATE   3/02/93                          GENERATION DATE   3/02/93

                                                                                

   JITCOMP          JIT COMPONENT                                              

   Oper                                W/C Op     Labor          Machine    R  

 S  No   Description                       Ty     Hours           Load      C  

             Material            Labor          Overhead           Total       

   010  MACHINE PACED STEP             MA1  8        .000000        .000000    

                  .0000000         .0000000         .0000000         .0000000  

                                                                               

                                                                               

                                                                               

                                                                               

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

                                                                               

                                                                               

 F2=Command          F3=Exit             F7=Material         F11=Summary       

 F12=Cost Elements                                                                                                                                              

 

 

This screen displays the calculation of material, labor and overhead costs for each operation in the routing for a manufactured JIT part.  You may enter an X in the input field to the left of the Total Cost field of any displayed operation number to display the operation detail screen for that operation.

BASE CURRENCY

Display only.  Displayed only in multi-currency environments.  The currency in which screen amounts are expressed.

SIMULATION TRIAL ID

Displayed only if a simulated cost type was specified on the select screen.  Identifies the simulation for which cost information is displayed.

EFFECTIVITY DATE

The routing in effect on this date was used to calculate the displayed information.

GENERATION DATE

The date on which the displayed costs were generated.

PART NUMBER/DESCRIPTION

Identifies the item whose cost information is displayed.

SELECT

Optional.  Type an X in this field and press Enter to view more detailed information about the corresponding operation.

OPERATION NUMBER

The operation sequence number from the routing.

DESCRIPTION/ W/C NO/ OP TY/ LABOR HOURS/ MACHINE LOAD/ R C/ MATERIAL COST/ LABOR COST/OVERHEAD COST/TOTAL COST

The detailed information used to calculate costs:

Description - Text describing the operation.

W/C No - Number of the workcenter where the operation is performed, as specified on the routing.  The material labor and overhead rates defined for this workcenter were used to calculate the costs.

Op Ty - The type of the operation.  Indicates if the operation is a master or standard operation.  Also indicates what type of overlap is allowed for the operation.

Labor Hours - The number of labor hours per unit used for this operation.

Machine Load - The machine load per unit incurred for the operation.

RC - The rate code used to calculate costs.

Material - Standard material cost incurred at this operation to produce one piece or batch of the part.

Labor - Standard labor cost incurred at this operation to produce one piece or batch of the part.

Overhead - Standard burden cost incurred at this operation to produce one piece or batch of the part.

Total - Material Cost + Labor Cost + Overhead Cost

COMMAND KEYS

Enter - Return to the select screen.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.

F7    - Display the material detail for the part.

F11   - Display summary costs for the part.

F12   - Display cost elements for the part.