MAC-PAC Homecontact ussupport login 
Documentation > MAC-PAC Reference Library > Manufacturing > Design Engineering > Screens > Engineering Change > DE160S02 - Detail

DE160S02 - Detail

 

 

WILLIAMS                      DESIGN ENGINEERING                       3/02/95

 DSP01                    ENGINEERING CHANGES MAINTENANCE                CHANGE

                                                                               

                                                                               

                                                                               

     Eng Change Order No    ECO13                                               

                                                                               

                                                                               

     Effectivity Date       080195                ECO Reason Code  03          

                                                                               

                                                  Planner Code     ROS         

                                                                               

     ECO Desc      NEW COPPER COIL TO BE PRESSED WILL RESULT IN LESS           

                   SCRAP DUE TO ITS NEW CHEMICAL MAKE-UP.                      

                                                                               

                                                                               

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

 F2=Command          F3=Exit             F4=Prompt           F9=Inquiry        

 F10=Function Select F15=Rekey Data                                            

                                                                               

 

This screen is used to add, change, or delete engineering change orders (ECOs).  For change transactions, at least one field must changed.

ENGINEERING CHANGE ORDER NUMBER

This display only field indicates the number of the engineering change order to be added, changed, or deleted.

EFFECTIVITY DATE

Required.  Enter the date on which the engineering change will take effect.  This date must not be entered as or changed to a date earlier than the current date.  If this date is changed and category C12 - ECO date update option is '1' or '2', then all product structure links using engineering change order number will be update with the new effectivity date.

REASON CODE

Optional.  Enter the reason for making this engineering change.  If entered, this code must be one of the reason codes defined on the Reference File ( category C04).

PLANNER CODE

Optional.  Enter identification of the person initiating this change.  If entered, this code must be one of the planner codes defined on the Reference File (category 235).

DESCRIPTION

Required.  Enter a description of the engineering change.  This field is user-defined.

COMMAND KEYS

Enter - Process transaction.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.

F4    - Display a list of values for the field where the cursor is positioned.  If you select one of the items from the list, it will be returned to the application screen.

F9    - Enter the Engineering Changes Inquiry program.

F10   - Return to the transaction select screen to select a different ECO number or maintenance function.

F15   - Exit this transaction to rekey screen data.