WILLIAMS DESIGN ENGINEERING 1/16/97
DSP01 ECO WHERE-USED INQUIRY ROUTING DETAIL
ECC002 TEST Effectivity Date
10/17/96
Oper O W/C ----- Effectivity -----
Plt Part Number No Ln T No I/O ECO Date
BEL WSPART01 001 00 960 IN ECC002 10/17/96
BEL WSPART01 002 00 1 AJ1 IN ECC002 10/17/96
F2=Command F3=Exit F9=Maintenance
This screen is displayed when Request Code 2 - Where Used in Routing - is selected on the Function Select screen.
EFFECTIVITY DATE
Display only. The data on which the engineering change will take effect.
PLANT
Display only. Used to identify the plant in which inquiry will be done. The plant must be valid (not blanks or nines) and the user must be authorized to the manufacturing company/warehouse associated with the plant (Reference File Category 409).
PART NUMBER
Display only. Must be a manufactured or transfer part on the Part Master file. The part number is the item that is manufactured using this routing. It was entered on the Function Select screen.
OPERATION NUMBER AND LINE
Display only. The operation number serves as a unique identification of the step and defines the sequence in which the steps are performed within the routing. A Line Number of '00' indicates a primary operation; a non-zero Line Number indicates an alternate operation.
OPERATION TYPE
Display only. The standard operation types are:
1 - Standard
2 - Master
3 - Setup only overlap
4 - Run time overlap
5 - Setup and run time overlap
6 - Fixed time no overlap
7 - Fixed time setup only overlap
8 - JIT
WORKCENTER NUMBER
Display only. The workcenter in which the operation is processed.
ENGINEERING CHANGE ORDER - IN
Display only. Identifies the ECO that brings an operation into effectivity. Must be defined on the ECO file.
EFFECTIVITY-IN DATE
Display only. For IN engineering changes, the first date the operation should appear in the part's routing. The date is system maintained if Reference File category N38 is 1 or 2.
ENGINEERING CHANGE ORDER - OUT
Display only. Identifies the engineering change that causes the operation to be removed from the routing. Must be defined on the ECO file.
EFFECTIVITY-OUT DATE
Display only. For OUT engineering changes, the date after which the operation should be removed from the part's routing. The date is system maintained if Reference File category N38 is 1 or 2.
COMMAND KEYS
F2 - Display a window where a fast path option or mnemonic can be entered. Fast path allows the next menu selection to be made directly from this screen. When the window is displayed, pressing F3 will remove it.
F3 - Exit program and return to menu.
F9 - Initiates Engineering Change Order File Maintenance from inquiry.
|