DE350S01 - Request

 

 

WILLIAMS    PLT BEL          DESIGN ENGINEERING                        5/04/94

 DSP01                 CUMULATIVE LEADTIME GENERATION REQUEST           REQUEST

                                                                               

                                                                               

                                                                               

                                                                                

                                                                               

                        Submit Request               N                         

                                                                               

                        Generate Cumulative Leadtime Y                         

                                                                               

                        Update RP Firm Horizon Days  Y                         

                                                                                

                        Effectivity Date              5/04/94                  

                                                                               

                        Requestor                    WILLIAMS                  

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

 F2=Command          F3=Exit             F17=New Plt                           

                                                                               

                                                                                                                                                                

 

 

This screen allows you to enter or update a cumulative leadtime generation request and/or update the requirements planning firm horizon days.

One request is allowed per plant at a time.  This request is stored on Reference File category K11.  If a request already exists for a plant, you can review and/or modify it using this screen.  You can review the request through the Reference File Maintenance and Reference File Inquiry conversations, but the only way to change a request is through this screen.

The generation will be performed when the batch job is submitted for processing.

PLANT

Required.  Cumulative leadtimes will be calculated for every part in this plant.  The plant must exist on the Warehouse Description File (IC170M), and you must be authorized to the company/warehouse associated with the plant.  This field defaults to the plant associated with your workstation ID.  You can change the plant by using the F17 (New Plant) function key.

SUBMIT REQUEST

Required.  Indicates whether or not leadtimes should be calculated for all parts in the plant.  Valid values are Y (yes) and N (no).  If you enter a Y in this field, the plant will be included next time the Cumulative Leadtime Generation batch job is submitted.  After the job is finished, the system will reset the field to N.  To delete a request before the batch job is submitted, change this field from Y to N.

GENERATE CUMULATIVE LEADTIME

Required.  Valid values are Y (yes) or N (no).  If you enter Y, the cumulative leadtime is calculated and updated for every part in a plant.  The cumulative leadtime includes both fixed and variable leadtimes.  For manufactured and build-thru parts, it includes the time required to manufacture or purchase all of the part's components.  If you enter N, the cumulative leadtime is not calculated.

UPDATE REQUIREMENTS PLANNING FIRM HORIZON DAYS

Required.  Valid values are Y (yes) or N (no).  If you enter Y, the Part Master RP Firm Horizon Days (which is used for planning purposes in the Requirements Planning module) will be calculated as being the same days as the cumulative leadtime days/horizon for the part.  If you enter N, the RP Firm Horizon Days is not updated.  It may be appropriate for you to enter N if you define this Firm Horizon Days field manually, or if you want the RP Firm Horizon Days date to be different from the cumulative leadtime date.

EFFECTIVITY DATE

Required.  Components in effect on this date will be used to determine the cumulative lead time for manufactured and build-thru parts.  This field defaults to today's date.

REQUESTOR

Optional.  The text in this field will be printed on the Cumulative Leadtime Generation Request report to help identify who requested the report.  It will also appear on the plant's Cumulative Leadtime Generation Request record (K11), so that anyone reviewing requests for the plant (or attempting to enter another request for the plant) will be able to identify who submitted this request.  No validation is performed.

COMMAND KEYS

Enter - Update the Reference File category K11 for the request.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.

F4    - Display a list of values for the field where the cursor is positioned.  If you select one of the items from the list, it will be returned to the application screen.

F17   - Change the plant in which the user is currently working.