WILLIAMS   PLT BEL            CAPACITY PLANNING                        2/01/92

 DSP01                     REPORT PERIOD DEFINITION                      DETAIL

                                                                               

                                                                               

 Per  No of       Per  No of       Per  No of       Per  No of       Per  No of

  No  Days         No  Days         No  Days         No  Days         No  Days 

  51     5         52     5         53     5         54     5         55     5 

  56     5         57     5         58     5         59     5         60     5 

  61     5         62     5         63     5         64     5         65     5 

  66     5         67     5         68     5         69     5         70     5 

  71     5         72     5         73     5         74     5         75     5 

  76     5         77     5         78     5         79     5         80     5 

  81     5         82     5         83     5         84     5         85     5 

  86     5         87     5         88     5         89     5         90     5 

  91     5         92     5         93     5         94     5         95     5 

  96     5         97     5         98     5         99     5        100     5 

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

 F2=Command          F3=Exit             F10=Periods 1-50    F15=Rekey Data    

                                                                               

 

This screen is used to define to the Capacity Planning module the length of the periods to be used for load summary inquiry and reporting.  Only working days (as set up on the shop calendar) will be considered.

This screen will only be displayed if periods 1-50 have all been defined on the previous screen.

PLANT

Display only.  The plant for which capacity reporting intervals are being defined.  It was entered on the first screen.

NUMBER OF DAYS PER PERIOD

Required.  Enter the number of days required in each load period.  You can define up to 100 periods in total, and there cannot be any gaps between periods.  The period load mask is used in the load summary and detail functions to accumulate load from a requested start date.

COMMAND KEYS

Enter - Process the period definition.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.

F10   - Return to the first screen to review periods 1-50 without updating periods 51-100.

F15   - Respecify all period lengths on this screen.