CP800S02 - Labor Detail

 

 

 WILLIAMS   PLT BEL            CAPACITY PLANNING                        1/18/96

 DSP01                        LOAD SUMMARY INQUIRY                        LABOR

                        LAST CP GENERATION DATE  0/00/00                       

                           FROM  1/18/96  TO 12/23/97                          

                                                                               

 Workcenter Number AAA SETUP                          Machine/Labor Paced   L  

 Department Number CP1     Hours Per Day 08           Include Setup In Load Y  

                                                                               

                             ------------ Percentage Load ------------         

  Period    Total   Effect   0                  100                 200        

   End      Load   Capacity  +---------+---------+---------+---------+         

  1/17/96    5504                                                               

  1/18/96       0       10    0%                                               

  1/19/96       0       10    0%                                               

  1/22/96       0       10    0%                                               

  1/23/96       0       10    0%                                               

  1/30/96      10       50    FFFF                                             

  2/06/96      10       50    FFFF                                              

  2/13/96      10       50    FFFF                                             

  2/20/96      20       50    FFFFFFFF                                        +

                                                                               

 F2=Command          F3=Exit             F8=W/C Inquiry      F11=Machine Summary

 F12=Load Detail                                                               

                                                                               

 

 

This screen is used to review at the summary level the labor load scheduled onto a workcenter.  The labor hours are compared with available capacity and presented graphically.

PLANT

Display only.  The plant where the workcenter is located.

LAST CP GENERATION DATE

The date on which the generation of planned labor requirements was last performed.  The load information displayed will not reflect changes to the order schedule which have been made since this date.  You may wish to re-run the CP Generation to obtain the most up-to-date load picture.  If Shop Floor Control is installed, load due to open and firmed orders will be completely current.  That due to planned orders will be current only as of the last generation date.

FROM (START DATE)

Display only.  The load was calculated beginning with this date.  Start date was specified on the function select screen.

TO (END DATE)

Display only.  The load has been calculated through this date.  End date was specified on the function select screen.

WORKCENTER NUMBER

Display only.  The workcenter for which load information is displayed.

MACHINE/LABOR PACED FLAG

Display only.  Indicates whether the workcenter is machine-paced (M) or labor-paced (L).

DEPARTMENT NUMBER

Display only.  The department where the workcenter is located.

HOURS PER DAY

Display only.  The standard number of hours available at the workcenter each day.

INCLUDE SETUP IN LOAD

Display only.  Specifies whether the load calculations include load from setup.  Values are Y (yes) and N (no).

PERIOD END DATE

Display only.  The cutoff date for each period.  The length of the time periods displayed is defined by the number of days per period in the period mask.  The first period represents all load before the start date entered on the select screen.

TOTAL LOAD

Display only.  The outstanding labor hours scheduled to be performed at the workcenter in each period. This may or may not include setup time, depending on the workcenter option.

EFFECTIVE CAPACITY

Display only.  The capacity for each period, calculated from the labor hours per day which was defined in the Effective Capacity maintenance conversation.

PERCENTAGE LOAD

Display only.  The graph shows total load as a percentage of total capacity for each period.  The letters in the graph represent open, firmed and planned order contribution to the outstanding workload.  The detailed operations which make up the summary totals may be reviewed by selecting the required period with an 'X' and pressing Command 12.

SELECT

Optional.  To view a detailed breakdown of the load for one period, type an X in this field and press F12.

COMMAND KEYS

Enter - Return to workcenter/period selection.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program.

F8    - Enter the Workcenter Inquiry program.

F11   - Review machine load summary for same workcenter and time range.

F12   - Review detailed operations comprising load for the selected summary period.