WILLIAMS   PLT PAD            CAPACITY PLANNING                        2/03/92

 DSP01                        LOAD DETAIL INQUIRY                        SELECT

                                                                                

                                                                               

                                                                               

                                                                               

                           Workcenter         W20                              

                                                                               

                           Period Start Date  120194                           

                                                                                

                           Period End Date    120794                           

                                                                               

                           Load Option                                         

                                                                               

                                                                               

                                                                                

                                                                               

                                                                               

                                                                               

                                                                               

                                                                               

 F2=Command          F3=Exit             F4=Prompt           F17=New Plant     

                                                                               

 

This screen is used to specify the workcenter and time period for which the detailed operations contributing labor or machine load are to be displayed.

PLANT

Required.  Used to identify the plant where the workcenters exist.  The plant must be valid (not blanks or nines) and the user must be authorized to the manufacturing company/warehouse associated with the plant (Reference File category 409).  Defaults to the plant assigned to the user ID, but may be changed by pressing Command 17.

WORKCENTER NUMBER

Required.  Enter the workcenter for which you wish to review details of the scheduled load. Load cannot be reviewed for an outside process workcenter.

PERIOD START DATE

Required.  Must be a working day on the Shop Calendar.  The start of the period for which operations contributing load to the workcenter will be displayed.

PERIOD END DATE

Required.  Must be a working day on the Shop Calendar.  The end of the period for which operations contributing load to the workcenter will be displayed.

LOAD OPTION

Optional.  Used to determine whether labor or machine load will be displayed first. Valid codes are: L     - Labor M     - Machine Blank - Display the type of load corresponding to pacing of the selected workcenter.

COMMAND KEYS

Enter - Display the detail screens.

F2    - Display a window where a fast path option or mnemonic can be entered.  Fast path allows the next menu selection to be made directly from this screen.  When the window is displayed, pressing F3 will remove it.

F3    - Exit program and return to menu.

F4    - Display a list of values for the field where the cursor is positioned.  If you select one of the items from the list, it will be returned to the application screen.

F17   - Used to change the plant in which the user is currently working.