Machine Load Summary

CP500B

 


 

DATE    2/03/92                              ANDERSEN SOFTWARE                                                              PAGE   3

TIME    8:55:11                                                                                                            PLANT BEL

REPORT CP500B                                        LOAD SUMMARY REPORT                                                     MACHINE

                                                 LAST CP GENERATION DATE  0/00/00

                                                   FROM  1/01/91 TO  2/03/92                        REQUESTOR  WILLIAMS

W/C                                    DEPT    M/L     INCL    EXCEPTION

NO    WORKCENTER DESCRIPTION            NO    PACED    SETUP   PERCENT

---   ------------------------------    ---     -        -      ---

IAL   LABOR-PACED WORKCENTER            D10     L        Y        5

 PERIOD    NO OF  ----------LOAD----------    EFFECT     LOAD   CUMULATIVE         -------------PERCENTAGE LOAD-------------

  END      DAYS   SETUP    RUN       TOTAL   CAPACITY      %    DIFFERENCE         0                  100                 200

--------    ---    ---    ------    ------    ------     ---     -------           +---------+---------+---------+---------+

12/31/90            10        10        20

 1/07/91      5      0        10        10         0      50           0            OOOOOOOOOO                 

 1/14/91      5     20        50        70         0      25           0            OOOOO                     

 1/21/91      5      5        15        20         0     100           0            OOOOOOOOOOOOOOOOOOOO      

                                                                           **  END OF WORKCENTER  **

                                                                            **  END OF REPORT  **

Purpose

This report provides machine setup and run load totals for planned and released orders per period by workcenter.  The total load is compared to the effective capacity for each period.

This report is requested on the Load Summary Report Request Screen (CP310S01).

Report Sequence

Workcenter Number (if all workcenters are requested).