Standard Operations

 

Setup Dependent
(Type 1)

In this example, the first operation could be any type.  The second operation is Standard (type 1).  All parts from the first operation are required before the setup of the second operation can begin.

Setup Independent
(Type 3)

In this example, the first operation could be any type.  The second operation is Setup Only Overlap (type 3).  Parts from the first setup are not required for setup.  However, all parts are required before the run of the second operation can begin.

Move/Queue Time

When move or queue times are involved in any processing, this time offsets the start time of the second operation.

How Standard Operations Are Scheduled.