Load for just-in-time steps is simple to calculate. Total labor load and total machine load are defined for each JIT step on a routing. This load is multiplied by the quantity to be produced to give the total load on the operation. (If batch sizes are used, the quantity is converted into a number of batches before the multiplication occurs).