Labor Requirements Generation
Labor requirements are generated based on the day(s) when the load occurs at a workcenter and any routing changes scheduled to go into effect during that period. If a workcenter change is planned during the time work is scheduled at an operation, two labor requirements records are created for that operation:
· The first labor requirement uses the workcenter in effect when the work begins. Its start date is the date when the operation begins, and its end date is the date when the change occurs.
· The second labor requirement uses the workcenter in effect when the work ends. Its start date is the date when the change occurs. Its end date is the last day production is scheduled for the operation.