Elements of Scheduled Lead Times
When scheduling production operations, four elements of lead time are used in the calculations:
· Move. The time taken to move components from an operation in one workcenter to the next operation in a different workcenter.
· Queue. The time taken to move components from one operation to the next in the same workcenter.
· Setup. The time to prepare an operation.
· Run. The actual elapsed run time for an operation.
The move and queue times are a buffer between consecutive operations. Move and queue times are mutually exclusive. They are applied as an offset before the start date of the next operation is calculated.