DATE 2/28/92 ANDERSEN SOFTWARE PAGE 1
TIME 21:32:13 MANUFACTURING ORDER DETAIL - MATERIAL PLANT BEL
REPORT IA800B REQUESTOR USERA
MO NUMBER BOTH101
PARENT PART NO MRP-PROGBOTH1 PROGRESSIVE PART (BOTH 1)
UNIT OF MEASURE EA
COMPONENT USG QUANTITY TOTAL POST
PART NUMBER DESCRIPTION CDE STANDARD COST TRAN ID ISSUED COST DATE
--------------- ------------------------- --- ----------------- ---------- -------------- ---------------- --------
MRP-COMPONENT MRP COMPONENT PART 1 C 5.8900000 USERA 100.000 589.00 1/08/92
COMPONENT TOTAL 100.000 589.00
ORDER TOTAL - MATERIAL COST OF RECEIPTS .00
- ACTUAL COST OF ISSUES 589.00
- BALANCE 589.00
** END OF REPORT **
|