Documentation >
MAC-PAC Reference Library >
Financials >
Inventory Accounting >
Reports >
Manning Efficiency Summary Report
Manning Efficiency Summary Report
IA660B
DATE 12/10/99 ** DEMAND ** PAGE 1
TIME 15:10:05 CUTOFF 10/12/99 CO
REPORT IA660B MANNING EFFICIENCY SUMMARY LOC
REQUESTOR MURRAY PLT
EFF
DPT WORKCENTER ACT HOURS STD HOURS VAR HOURS ACTUAL COST STANDARD COST VARIANCE COST PCT
--- ---------------------------- ------------ ------------ ------------ ----------------- ----------------- ----------------- ------
*****NO RECORDS PROCESSED*****
** END OF REPORT **
|
Purpose
This report lists the actual, standard, and variance manning costs for each manufacturing order. In all cases, the cost equals the corresponding hours times the labor rate.
Both open and closed orders are included in the report. In addition, the hours used to calculate the costs and the efficiency rate are provided for each workcenter. Hour subtotals, cost subtotals, and efficiency rate are also given for each department, plant, and company. The Cutoff field will be displayed only in a demand post or trial demand (where the cutoff date is filled in).
Report Sequence
Company, plant, department, workcenter.