Documentation >
MAC-PAC Reference Library >
Financials >
Inventory Accounting >
Reports >
Job Cost Report - Summary and Plant Summary
Job Cost Report - Summary and Plant Summary
JA520B
DATE 9/01/92 ANDERSEN SOFTWARE PAGE 25
TIME 12:25:29 JOB COST REPORT CURRENCY CODE BEF
REPORT JA520B PLANT SUMMARY REQUESTOR WILLIAMS
JOB JOB001X STANDARD JOB INTROSPECT XXX PROJECT MANAGER STATUS O
CUSTOMER C04 APPELMANS SC JOB GROUP
PLANT BEL VARIANCE FROM PLAN
--------------------------------------
PLANNED ACTUAL PROJECTED ACTUAL PROJECTED
------------------ ------------------ ------------------ ------------------ ------------------
MATERIAL 4,100.00 .00 .00 4,100.00- 4,100.00-
LABOR .00 .00 .00 .00 .00
OVERHEAD .00 .00 .00 .00 .00
MISCELLANEOUS COSTS .00 .00 .00 .00 .00
ADDITIONAL JOB CHARGES .00 .00 .00 .00 .00
------------------ ------------------ ------------------ ------------------ ------------------
TOTAL COST OF JOB 4,100.00 .00 .00 4,100.00- 4,100.00-
================== ================== ================== ================== ==================
PERCENT COMPLETE 0%
|
Purpose
This report lists planned, actual, and projected costs for a job. It also indicates variances between both actual and planned and projected and planned costs. These costs are further divided by plant into material, labor, overhead, miscellaneous costs, and additional job charges. If the Shop Floor Module is installed, a percent complete will be calculated and printed at the bottom of the report. The report can be requested for a specific job, a project manager, a job group, or all jobs.
A summary report for each job across all plants is also generated.
Report Sequence
Job Group, Project Manager, Job, Plant.